Installation Roadmap
This table lists the steps to install the Cisco NCS 4009 chassis and its components and prepare the system for operation. Use this table as a checklist to ensure that all components are properly installed in the correct order. For information about a step, see the respective book or section of this installation guide.
Step |
See |
||
---|---|---|---|
Verify that the chassis is secured in the rack.
|
Cisco Network Convergence System 4000 Series Unpacking, Moving, and Securing Guide |
||
Ground the chassis. |
|||
Verify that the power components are installed. |
|||
Verify that the ECU is installed. |
|||
Verify that the fan trays are installed. |
|||
Connect the AC or DC power cord. |
|||
Power on the chassis. |
|||
Install cards and remaining components in the chassis. |
Installing Route Processor Cards, Fabric Cards, and Line Cards |
||