Prerequisites and Guidelines
Before you proceed with deploying the Nexus Dashboard cluster, you must:
-
Review and complete the general prerequisites described in Deployment Overview and Requirements.
Note that this document describes how to initially deploy the base Nexus Dashboard cluster. If you want to expand an existing cluster with additional nodes (such as
worker
orstandby
), see the "Infrastructure Management" chapter of the Cisco Nexus Dashboard User Guide instead, which is available from the Nexus Dashboard UI or online at Cisco Nexus Dashboard User GuideIf you are looking to completely re-image the server, for example in case you cannot log in as the
rescue-user
for manual recovery, see the "Troubleshooting" chapter of the Cisco Nexus Dashboard User Guide. -
Review and complete any additional prerequisites described in the Release Notes for the services you plan to deploy.
-
Ensure you are using the following hardware and the servers are racked and connected as described in Cisco Nexus Dashboard Hardware Setup Guide.
The physical appliance form factor is supported on the UCS-C220-M5 and UCS-C225-M6 original Nexus Dashboard platform hardware only. The following table lists the PIDs and specifications of the physical appliance servers:
Table 1. Supported UCS-C220-M5 Hardware PID
Hardware
SE-NODE-G2=
-
UCS C220 M5 Chassis
-
2x 10-core 2.2GHz Intel Xeon Silver CPU
-
256 GB of RAM
-
4x 2.4TB HDDs
400GB SSD
1.2TB NVME drive
-
UCS Virtual Interface Card 1455 (4x25G ports)
-
1050W power supply
SE-CL-L3
A cluster of 3x SE-NODE-G2=
appliances.Table 2. Supported UCS-C225-M6 Hardware PID
Hardware
ND-NODE-L4=
-
UCS C225 M6 Chassis
-
2.8GHz AMD CPU
-
256 GB of RAM
-
4x 2.4TB HDDs
960GB SSD
1.6TB NVME drive
-
Intel X710T2LG 2x10 GbE (Copper)
Intel E810XXVDA2 2x25/10 GbE (Fiber Optic)
-
1050W power supply
ND-CLUSTER-L4
A cluster of 3x ND-NODE-L4=
appliances.Note
The above hardware supports Nexus Dashboard software only. If any other operating system is installed, the node can no longer be used as a Nexus Dashboard node.
The UCS-C225-M6 servers are supported with Nexus Dashboard release 2.3(2) or later.
-
-
Ensure that you are running a supported version of Cisco Integrated Management Controller (CIMC).
The minimum supported and recommended versions of CIMC are listed in the "Compatibility" section of the Release Notes for your Nexus Dashboard release.
-
Ensure that Serial over LAN (SOL) is enabled in CIMC.
SOL is required for the
connect host
command, which you use to connect to the node to provide basic configuration information. -
Ensure that all nodes are running the same release version image.
-
If your Nexus Dashboard hardware came with a different release image than the one you would like to deploy, we recommend deploying the cluster with the existing image first and then upgrading it to the desired release.
For example, if the hardware you received came with Release 2.0.1 image pre-installed, but you want to deploy Release 2.1.1 instead, we recommend:
-
First, bring up the Release 2.0.1 cluster, as described in the following section.
-
Then upgrade to Release 2.1.1, as described in Upgrading Nexus Dashboard.
-
You must have at least a 3-node cluster. Additional worker nodes can be added for horizontal scaling if required by the type
and number of applications you will deploy. For maximum number of worker
and standby
nodes in a single cluster, see the Release Notes for your release.